Program plans
A cloud migration plan fails in one of two places, and neither of them is the move itself. It fails where an application nobody has dispositioned sits in a wave it was never meant to be in, and it fails where the rollback was written and never tested.
What follows is the actual rule set this agent applies to a migration, and the working days each stage is given. It is not a template. It is what runs every weekday morning against a real plan, and it is published here because nobody selling you a cloud migration template has one.
Every program owes these twelve, in this order. The days are working days and they are the starting point the scheduler reasons from, not a quote: a real program moves them, and the point of writing them down is that moving one has to be a decision somebody made.
| Stage | Working days |
|---|---|
| Initiate | ten working days |
| Discover | fifteen working days |
| Requirements | twenty working days |
| Design | twenty working days |
| Build | 40 working days |
| SIT | fifteen working days |
| UAT | fifteen working days |
| Training | ten working days |
| Cutover rehearsal | five working days |
| Go live | one working day |
| Hypercare | twenty working days |
| Benefits | twenty working days |
A migration adds four stages the baseline does not have, and all four are about proving the move works before it has to.
| Stage | Working days |
|---|---|
| Migration design | fifteen working days |
| Data migration | twenty working days |
| Dry run | five working days |
| Rollback plan | five working days |
These are read out of the engine rather than written here, so the table is what actually runs. Seven rules apply to this kind of program on top of the nineteen every program owes, and all of them are checked against every row, every weekday morning.
| Rule | Kind | What it means |
|---|---|---|
MG-001 | Order | Migration design cannot start until Discover is done. |
MG-002 | Order | Data migration cannot start until Migration design is done. |
MG-003 | Order | Dry run cannot start until Data migration is done. |
MG-004 | Lead time | Five working days must pass between Dry run and Cutover rehearsal. |
MG-005 | Lead time | Ten working days must pass between Rollback plan and Go live. |
MG-010 | Evidence | Dry run cannot close until the evidence is attached: dry run report, reconciliation. |
MG-011 | Evidence | Rollback plan cannot close until the evidence is attached: rollback test. |
Underneath them sit the nineteen baseline rules every program is held to, whatever it is: design does not complete without sign-off, SIT does not complete without results, go live does not complete without a recorded go/no-go. The documentation has the workbook those rows live in.
| Rule | Kind | What it means |
|---|---|---|
BR-001 | Order | Discover cannot start until Initiate is done. |
BR-002 | Order | Requirements cannot start until Discover is done. |
BR-003 | Order | Design cannot start until Requirements is done. |
BR-004 | Order | Build cannot start until Design is done. |
BR-005 | Order | SIT cannot start until Build is done. |
BR-006 | Lead time | Three working days must pass between SIT and UAT. |
BR-007 | Lead time | Five working days must pass between UAT and Training. |
BR-008 | Order | Cutover rehearsal cannot start until Training is done. |
BR-009 | Lead time | Five working days must pass between Cutover rehearsal and Go live. |
BR-010 | Lead time | Two working days must pass between Training and Go live. |
BR-011 | Order | Hypercare cannot start until Go live is done. |
BR-012 | Lead time | Twenty working days must pass between Hypercare and Benefits. |
BR-020 | Evidence | Design cannot close until the evidence is attached: design sign-off. |
BR-021 | Evidence | SIT cannot close until the evidence is attached: test result. |
BR-022 | Evidence | UAT cannot close until the evidence is attached: uat sign-off. |
BR-023 | Evidence | Training cannot close until the evidence is attached: attendance. |
BR-024 | Evidence | Cutover rehearsal cannot close until the evidence is attached: rehearsal report. |
BR-025 | Evidence | Go live cannot close until the evidence is attached: go/no-go decision. |
BR-030 | Freeze | No change goes in inside ten working days of Go live. |
The demo builds cloud migration program in front of you from the rules above, then hands you the real screens on the one it just built. There is something genuinely wrong in it on purpose, and it does not tell you what.
Watch it build one, or pick a different kind of program. No card, nothing to install.
Describe it in a sentence and it builds the plan, checks your date against these rules before you commit to it, and asks the owners every weekday after. The first thirty days are free.