Most ERP plans are right on the day they are written. They stop being right between the meetings: a fit gap sits undecided, a date moves a day at a time, and nobody sees the go live date go until the quarter it was in has gone.
Below is the sequence a package implementation owes, the working days each stage is given before anything is negotiated, and the rules the plan is measured against every morning. It is the real rule set, not an illustration of one.
Every program owes these twelve, in this order. The days are working days and they are the starting point the scheduler reasons from, not a quote: a real program moves them, and the point of writing them down is that moving one has to be a decision somebody made.
| Stage | Working days |
|---|---|
| Initiate | ten working days |
| Discover | fifteen working days |
| Requirements | twenty working days |
| Design | twenty working days |
| Build | 40 working days |
| SIT | fifteen working days |
| UAT | fifteen working days |
| Training | ten working days |
| Cutover rehearsal | five working days |
| Go live | one working day |
| Hypercare | twenty working days |
| Benefits | twenty working days |
A package implementation adds two stages that a build does not have, and both of them are where the scope is actually decided.
| Stage | Working days |
|---|---|
| Fit gap | fifteen working days |
| Configuration | 30 working days |
These are read out of the engine rather than written here, so the table is what actually runs. Seven rules apply to this kind of program on top of the nineteen every program owes, and all of them are checked against every row, every weekday morning.
| Rule | Kind | What it means |
|---|---|---|
PK-001 | Order | Fit gap cannot start until Requirements is done. |
PK-002 | Order | Design cannot start until Fit gap is done. |
PK-003 | Order | Configuration cannot start until Design is done. |
PK-004 | Order | SIT cannot start until Configuration is done. |
PK-005 | Lead time | Fifteen working days must pass between Configuration and Go live. |
PK-010 | Evidence | Fit gap cannot close until the evidence is attached: gap decision. |
PK-011 | Evidence | Configuration cannot close until the evidence is attached: config workbook. |
Underneath them sit the nineteen baseline rules every program is held to, whatever it is: design does not complete without sign-off, SIT does not complete without results, go live does not complete without a recorded go/no-go. The documentation has the workbook those rows live in.
| Rule | Kind | What it means |
|---|---|---|
BR-001 | Order | Discover cannot start until Initiate is done. |
BR-002 | Order | Requirements cannot start until Discover is done. |
BR-003 | Order | Design cannot start until Requirements is done. |
BR-004 | Order | Build cannot start until Design is done. |
BR-005 | Order | SIT cannot start until Build is done. |
BR-006 | Lead time | Three working days must pass between SIT and UAT. |
BR-007 | Lead time | Five working days must pass between UAT and Training. |
BR-008 | Order | Cutover rehearsal cannot start until Training is done. |
BR-009 | Lead time | Five working days must pass between Cutover rehearsal and Go live. |
BR-010 | Lead time | Two working days must pass between Training and Go live. |
BR-011 | Order | Hypercare cannot start until Go live is done. |
BR-012 | Lead time | Twenty working days must pass between Hypercare and Benefits. |
BR-020 | Evidence | Design cannot close until the evidence is attached: design sign-off. |
BR-021 | Evidence | SIT cannot close until the evidence is attached: test result. |
BR-022 | Evidence | UAT cannot close until the evidence is attached: uat sign-off. |
BR-023 | Evidence | Training cannot close until the evidence is attached: attendance. |
BR-024 | Evidence | Cutover rehearsal cannot close until the evidence is attached: rehearsal report. |
BR-025 | Evidence | Go live cannot close until the evidence is attached: go/no-go decision. |
BR-030 | Freeze | No change goes in inside ten working days of Go live. |
The demo builds ERP implementation program in front of you from the rules above, then hands you the real screens on the one it just built. There is something genuinely wrong in it on purpose, and it does not tell you what.
Watch it build one, or pick a different kind of program. No card, nothing to install.
Describe it in a sentence and it builds the plan, checks your date against these rules before you commit to it, and asks the owners every weekday after. The first thirty days are free.